EPMFAQ Forums - Connect with the EPM Community  

Go Back   EPMFAQ Forums - Connect with the EPM Community > Microsoft Project Forums > Project Server 2007


Reply
 
LinkBack Thread Tools Display Modes
  #1 (permalink)  
Old 11-08-2008, 01:04 PM
Junior Member
 
Join Date: Nov 2008
Posts: 2
Thanks: 0
Thanked 0 Times in 0 Posts
Question Can multiple users report status on a task without taking 'ownership'?

Hi all,

This has me stumped, so any help/suggestions would be greatly appreciated. The scenario I need to enable is this:

1. The PM assigns a 20h Task to a team of people, not knowing who will actually be doing the work.

2. Team Member A does 12h work on the Task and Team Member B does 6h. They both submit status updates back to the PM.

3. The PM approves the two updates and the plan now shows Remaining Work as 2h.

The above scenario may sound straightforward but I can't seem to configure Project to enable this.

- Using Team Resources allows the PM to assign the Task appropriately, but the Task doesn't appear in Team Member's My Tasks unless they specifically 'Self-assign team tasks'. When they do, and it's approved by the PM, the Resource Assignment changes to their name. If Team Member B wants to add hours to that task as well, they need to manually add a new task to their My Tasks and find the Task. But the real problem is that when they add their 6h to the Task, the overall work becomes 26h (i.e. the original 20h stays with Team Member A so Team Member B's 6h work is in added to the Task's work.)

- I tried manually listing both resources against the task (i.e. not use Team Resources feature) and put 10h against each resource. Team Member A has done 12 hours instead of their allocated 10h, so the total work for the task becomes 22h instead of 20h (with Team Member B listed as having 4h remaining)

Does anyone have suggestions on other things I could try?

Many thanks,

Ben








Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Sponsored links
  #2 (permalink)  
Old 11-13-2008, 01:00 PM
ssanderlin's Avatar
EPMFAQ Founder/Owner
 
Join Date: Feb 2008
Location: Quakertown, PA
Posts: 171
Thanks: 0
Thanked 17 Times in 17 Posts
Default

Quote:
Originally Posted by BenM View Post
Hi all,

This has me stumped, so any help/suggestions would be greatly appreciated. The scenario I need to enable is this:

1. The PM assigns a 20h Task to a team of people, not knowing who will actually be doing the work.

2. Team Member A does 12h work on the Task and Team Member B does 6h. They both submit status updates back to the PM.

3. The PM approves the two updates and the plan now shows Remaining Work as 2h.

The above scenario may sound straightforward but I can't seem to configure Project to enable this.

- Using Team Resources allows the PM to assign the Task appropriately, but the Task doesn't appear in Team Member's My Tasks unless they specifically 'Self-assign team tasks'. When they do, and it's approved by the PM, the Resource Assignment changes to their name. If Team Member B wants to add hours to that task as well, they need to manually add a new task to their My Tasks and find the Task. But the real problem is that when they add their 6h to the Task, the overall work becomes 26h (i.e. the original 20h stays with Team Member A so Team Member B's 6h work is in added to the Task's work.)

- I tried manually listing both resources against the task (i.e. not use Team Resources feature) and put 10h against each resource. Team Member A has done 12 hours instead of their allocated 10h, so the total work for the task becomes 22h instead of 20h (with Team Member B listed as having 4h remaining)

Does anyone have suggestions on other things I could try?

Many thanks,

Ben
The behavior you see in Scenario One is expected -- team resources don't support multiple team members self-assigning. In your case, I would recommend that you use Scenario 2.

The behavior you see in Scenario Two is also expected. The PM needs to adjust the remaining work for either the task or just Team Member B down to 8h. There is a logical reason for this. When you input assignment Actual Work, Project considers each assignment separately. In this case, it adds the extra 2h to the resource's Work value, which is why the task's Work expands to 22h from 20h. If you want to maintain the task's Work at 20h, you need to reduce Remaining Work for either the task or the assignment by 2h.
__________________
Stephen Sanderlin
Founder/Owner - EPMFAQ
VP of Technology - MSProjectExperts
Microsoft Project MVP

If you found this message useful, please click the Thanks button in the post!

This electronic message, along with any information, advice, and opinions it contains, are mine alone and are not representative of my employer. All information is provided in "GOOD FAITH" and on an "AS IS" basis only. I provide no presentations or warranties, express or implied, including implied warranties of fitness for a particular purpose, merchantability, title, and noninfringement. I strongly advise you to extensively test any changes, workarounds, or techniques described herein on a development system prior to implementation in a production environment, and you are hereby notified that I bear no responsibility whatsoever for any loss, harm, or otherwise negative outcomes resulting from your actions, whether or not said actions were a result of this electronic message, directly or indirectly.
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
The Following User Says Thank You to ssanderlin For This Useful Post:
Ahmed Khatib (09-08-2009)
  #3 (permalink)  
Old 11-17-2008, 10:19 AM
Junior Member
 
Join Date: Nov 2008
Posts: 2
Thanks: 0
Thanked 0 Times in 0 Posts
Default

Thanks Stephen,

I'm trying to use Project Server for an agile/scrum type development environment, but I guess the PMs are just going to have to update their assignment info regularly..

Cheers,
Ben
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On
Forum Jump


All times are GMT -4. The time now is 01:55 PM.


Powered by: vBulletin®
Copyright ©2000 - 2012, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO 3.2.0
Ad Management by RedTyger

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24