Originally Posted by agriffin I have found the problem. If the Actual Start Date for the task is set, then the Start Date will not change if the Constraint Date is changed. | Precisely correct. I'm glad you found a resolution!
__________________ Stephen Sanderlin
Founder/Owner - EPMFAQ
Principal Consultant - MSProjectExperts If you found this message useful, please click the Thanks button in the post!
This electronic message, along with any information, advice, and opinions it contains, are mine alone and are not representative of my employer. All information is provided in "GOOD FAITH" and on an "AS IS" basis only. I provide no presentations or warranties, express or implied, including implied warranties of fitness for a particular purpose, merchantability, title, and noninfringement. I strongly advise you to extensively test any changes, workarounds, or techniques described herein on a development system prior to implementation in a production environment, and you are hereby notified that I bear no responsibility whatsoever for any loss, harm, or otherwise negative outcomes resulting from your actions, whether or not said actions were a result of this electronic message, directly or indirectly. |