EPMFAQ Forums - Connect with the EPM Community  

Go Back   EPMFAQ Forums - Connect with the EPM Community > Microsoft Project Forums > Project 2007 Development


Reply
 
LinkBack Thread Tools Display Modes
  #1 (permalink)  
Old 11-20-2008, 03:57 AM
Junior Member
 
Join Date: Nov 2008
Posts: 9
Thanks: 0
Thanked 0 Times in 0 Posts
Question

Hi all,

I have a query regarding Cost Resources.

We have added a type of resource in our application called 'Miscellaneous' that must be mapped to a Cost Resource in Microsoft Project.

As of now, let's assume that for every Misc. Resource, I create a counterpart in MSP's Enterprise Resource Pool. First question: Can I set the default assignment owner (as myself) for such a Cost Resource during creation in the Enterprise Pool?

Now let's assume I can do that. Then I proceed to import that cost resource into the Project Team (which includes myself) and create an assignment to the respective tasks which include it.

We have a requirement that we should be able to record Actual Cost incurred over that Cost Resource Assignment during the execution of the project. The problem is, I'm unable to locate that assignment in the ChangeXML sample program.

Can the Status Update mechanism be used to update Actual Costs incurred over Cost Resource Assignments? If not, what is the solution to my requirement? ie: How does one record Actual Cost incurred over a Cost Resource through the PSI?

Regards,

Subramanian








Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Sponsored links
  #2 (permalink)  
Old 11-24-2008, 01:04 AM
Junior Member
 
Join Date: Nov 2008
Posts: 9
Thanks: 0
Thanked 0 Times in 0 Posts
Default

I've tried the following stuff, none of which seems to work.

1. I've tried setting myself as the Default_Assignment_Owner for the Cost resource when I create it in the Enterprise pool, but I'm not able to do that through PWA/Project Professional Client.

2. I've tried adding myself as Assignment Owner for the assignment in the specific project though Project Professional, but that field shows up as disabled/un-editable.

3. Through the Statusing Web Service, I've tried ReadStatus() to read the list of assignments I'm eligible to post status updates for, but the cost resource assignment alone is not visible. If i disregard that, and construct ChangeXML to update actual cost for that assignment_uid of the cost resource anyway, and try to post the status update, it throws back an exception. (Invalid Assn_Uid)

4. I've tried reading in the ProjectDataSet, modifying the ASSN_ACT_COST or the ASSN_ACT_WORK for that assignment and using QueueUpdateProject() to update those fields, but that throws me back an exception as well, saying 'ProjectCannotEditCostResource' with Error code 1050.

Running out of ideas. Posted it on several blogs and the Project.Developer NewsGroup, no replies till now.

Best Regards,

Subramanian
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
  #3 (permalink)  
Old 12-13-2008, 03:40 AM
ssanderlin's Avatar
EPMFAQ Founder/Owner
 
Join Date: Feb 2008
Location: Quakertown, PA
Posts: 171
Thanks: 0
Thanked 17 Times in 17 Posts
Default

For the edification of those in the forum, Brian Smith answered this question here: Brian Smith's Project Support WebLog : Adding Timephased Actual Work through the PSI
__________________
Stephen Sanderlin
Founder/Owner - EPMFAQ
VP of Technology - MSProjectExperts
Microsoft Project MVP

If you found this message useful, please click the Thanks button in the post!

This electronic message, along with any information, advice, and opinions it contains, are mine alone and are not representative of my employer. All information is provided in "GOOD FAITH" and on an "AS IS" basis only. I provide no presentations or warranties, express or implied, including implied warranties of fitness for a particular purpose, merchantability, title, and noninfringement. I strongly advise you to extensively test any changes, workarounds, or techniques described herein on a development system prior to implementation in a production environment, and you are hereby notified that I bear no responsibility whatsoever for any loss, harm, or otherwise negative outcomes resulting from your actions, whether or not said actions were a result of this electronic message, directly or indirectly.
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On
Forum Jump


All times are GMT -4. The time now is 07:52 AM.


Powered by: vBulletin®
Copyright ©2000 - 2010, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO 3.2.0
Ad Management by RedTyger

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24