Quote:
Originally Posted by agriffin View Post
How does the % Complete get calculated?
Brian Smith has a good example here.

FTA:
Quote:
An example will help. Assume a 10 day task with 8 hours work per day - 80 hours. If at the end of the first day the resource has completed 8 hours work then both % complete and % work complete are 10% (1 day out of 10 for duration and 8 hours work out of 80 for work). If however the resource only completes 7.5 hours of work we see a difference. Project will assume that this is all the work being carried out on day 1 so will need to extend the duration by half an hour (0.0625 days). So the % complete is now 1 day out of 10.06 days (9.94% - displayed as 10% in Project Center) and the % work complete is 7.5 hours out of 80 hours (9.375% - displayed as 9% in My Tasks).








__________________
Stephen Sanderlin
Founder/Owner - EPMFAQ
Principal Consultant - MSProjectExperts

If you found this message useful, please click the Thanks button in the post!

This electronic message, along with any information, advice, and opinions it contains, are mine alone and are not representative of my employer. All information is provided in "GOOD FAITH" and on an "AS IS" basis only. I provide no presentations or warranties, express or implied, including implied warranties of fitness for a particular purpose, merchantability, title, and noninfringement. I strongly advise you to extensively test any changes, workarounds, or techniques described herein on a development system prior to implementation in a production environment, and you are hereby notified that I bear no responsibility whatsoever for any loss, harm, or otherwise negative outcomes resulting from your actions, whether or not said actions were a result of this electronic message, directly or indirectly.
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Sponsored links
Reply

Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On
Forum Jump


All times are GMT -4. The time now is 04:24 PM.


Powered by: vBulletin®
Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO 3.2.0
Ad Management by RedTyger

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24