Quote:
Originally Posted by agriffin How does the % Complete get calculated? | Brian Smith has a good example here.
FTA: Quote: |
An example will help. Assume a 10 day task with 8 hours work per day - 80 hours. If at the end of the first day the resource has completed 8 hours work then both % complete and % work complete are 10% (1 day out of 10 for duration and 8 hours work out of 80 for work). If however the resource only completes 7.5 hours of work we see a difference. Project will assume that this is all the work being carried out on day 1 so will need to extend the duration by half an hour (0.0625 days). So the % complete is now 1 day out of 10.06 days (9.94% - displayed as 10% in Project Center) and the % work complete is 7.5 hours out of 80 hours (9.375% - displayed as 9% in My Tasks).
|
__________________ Stephen Sanderlin
Founder/Owner - EPMFAQ
Principal Consultant - MSProjectExperts If you found this message useful, please click the Thanks button in the post!
This electronic message, along with any information, advice, and opinions it contains, are mine alone and are not representative of my employer. All information is provided in "GOOD FAITH" and on an "AS IS" basis only. I provide no presentations or warranties, express or implied, including implied warranties of fitness for a particular purpose, merchantability, title, and noninfringement. I strongly advise you to extensively test any changes, workarounds, or techniques described herein on a development system prior to implementation in a production environment, and you are hereby notified that I bear no responsibility whatsoever for any loss, harm, or otherwise negative outcomes resulting from your actions, whether or not said actions were a result of this electronic message, directly or indirectly. |