View Single Post
  #9 (permalink)  
Old 12-10-2008, 02:49 AM
subbucse subbucse is offline
Junior Member
 
Join Date: Nov 2008
Posts: 9
Thanks: 0
Thanked 0 Times in 0 Posts
Default Another suggestion for P14

As of now, Cost resources are useless when it comes to recording Time-Phased Actual Work (Cost) done, because Status Update does not support them at all. Once again, we need to depend on Project Professional.

This I feel would be a great improvement.
Reply With Quote