My customer is an immature organisation just introducing project management and using a PPM tool to drive it. They create fixed duration tasks because they are managing the start and end dates without concerning themselves who is allocated to the tasks. In other words they manage time and not effort. This makes it impossible for them to use MSP. Open Workbench might be a better option !