Originally Posted by ssanderlin The Tasks section is derived from the Tasks within PWA, not within a PWS "Tasks" list. Similarly, Status Reports refer to those in PWA, not those within a PWS.
If you want this other information to show, you would need to create your own Reminders webpart. |
Hi Stephen
Thanks very much for your reply. I'm a bit new to Project Server 2007, so don't mind me if I need some clarification.
I thought tasks were universal across the collections of Project Web Sapces in Project Server. Is there a difference between the Tasks in PWA and the tasks in a Project Work Space (PWS)? How do you differentiate between the two types of Task?
Why does Risks behave differently for the Reminders web part. I can see a list of outstanding Risks assigned to a user associated in PWSs. There seems to be no difference between PWA risks and PWS risks.