The Start Date can not be changed in the PSI, it is read-only. But, I could try changing the Actual Start Date with the Constraint Date in order to make sure that the Start Date gets pushed to where it needs to be.
The client that I am doing this project for is using project at a very basic level, so there shouldn't be any actuals except for the Actual Start Date, Actual Finish Date, and the Work Percent Complete. |