Quote:
Originally Posted by Isuva View Post
Hi,

In Project pro 2007 you can't resources task using 0h of work without the task is changed to as a milestone. This is a problem when you have the task that last the hole year like Sick leave and you just want to give the place to report hours not resource any.

Is this a bug or just a feature?

Does anyone have any work around?
You should be able to set set the Milestone field for the task to No after you set either Duration or Work to 0d or 0h, respectively.

Are you doing your work in the context of a larger Project Server 2007 deployment, or are you using it totally standalone?
__________________
Stephen Sanderlin
Founder/Owner - EPMFAQ
VP of Technology - MSProjectExperts
Microsoft Project MVP

If you found this message useful, please click the Thanks button in the post!

This electronic message, along with any information, advice, and opinions it contains, are mine alone and are not representative of my employer. All information is provided in "GOOD FAITH" and on an "AS IS" basis only. I provide no presentations or warranties, express or implied, including implied warranties of fitness for a particular purpose, merchantability, title, and noninfringement. I strongly advise you to extensively test any changes, workarounds, or techniques described herein on a development system prior to implementation in a production environment, and you are hereby notified that I bear no responsibility whatsoever for any loss, harm, or otherwise negative outcomes resulting from your actions, whether or not said actions were a result of this electronic message, directly or indirectly.
Reply With Quote