Quote:
Originally Posted by darrellctaylor View Post
I have a couple of accounts that will not display any task assignments. I can assign a task to the individual, but when I log in under that account, it says that I have no tasks.
Darrell,

What is the Default Assignment Owner of the resources you are having trouble with? It may be blank, in which case you need to set it to the name of the resource.

Steve

Moderator note: Spawned this thread from the original to maintain topic separation.








__________________
Stephen Sanderlin
Founder/Owner - EPMFAQ
VP of Technology - MSProjectExperts
Microsoft Project MVP

If you found this message useful, please click the Thanks button in the post!

This electronic message, along with any information, advice, and opinions it contains, are mine alone and are not representative of my employer. All information is provided in "GOOD FAITH" and on an "AS IS" basis only. I provide no presentations or warranties, express or implied, including implied warranties of fitness for a particular purpose, merchantability, title, and noninfringement. I strongly advise you to extensively test any changes, workarounds, or techniques described herein on a development system prior to implementation in a production environment, and you are hereby notified that I bear no responsibility whatsoever for any loss, harm, or otherwise negative outcomes resulting from your actions, whether or not said actions were a result of this electronic message, directly or indirectly.
Reply With Quote
Sponsored links